It is recommended that you continually monitor
your servers' CPU, memory, and storage usage. When capacity is reached,
consider moving tenants to a new host server.
The host installation
package installs and configures the new host, including the settings
that will automatically connect the new host to your existing main
server.
You can use the same package for all hosts that you
want to add, unless you need to change the server's External Host
Name or the default admin. In this case, you need to create a new
host installer package for each host.
You access a new host
with the multi-tenant default admin credentials that generates the
host installation file.
All machines (hosts and main accounts)
must be time synced, even if they are located in different time
zones.
Run all installation commands as root user.